What Are the Eleven Required Fields on a Contractor Invoice?

What Does a General Contractor Invoice Look Like?

Most read top to bottom in five blocks. The header carries the word Invoice, the number, and the date. The parties block carries your details on the left and the client's on the right. The job block carries the site address and a short scope reference tied to the contract. The line item table carries labor, materials, and change orders with quantities, rates, and extended amounts. The footer carries subtotal, tax, total due, payment terms, due date, and payment instructions.

For progress billing on larger jobs, add three columns to the line item table: the scheduled value for that phase, the percentage complete this period, and the amount previously billed. That structure lets the client see what they have already paid without pulling old invoices.

What Supporting Documents Come with Construction Invoices?

Construction invoices commonly travel with lien waivers, daily logs, progress reports, change orders, and purchase orders. On residential work you rarely need all of them. On commercial work, sending the invoice without the lien waiver is the fastest way to have it held.

Ask at contract signing what the client's accounts payable process requires. A client who needs a conditional lien waiver with every draw will tell you. Building that into your invoice routine costs nothing up front and saves weeks later.

What Common Invoicing Mistakes Delay Payment?

How Do You Invoice as a Contractor?

  1. Start from a template so the field list is already built and you are not rebuilding the layout each time.
  2. Fill the header: invoice number, issue date, your business details, and license number.
  3. Fill the parties block with the contracting entity and the job site address.
  4. Enter labor by hours and rate, or by contracted phase amount.
  5. Enter materials with quantity and unit cost.
  6. Add each approved change order as its own line with its number and approval date.
  7. Apply sales tax to the taxable lines for your state.
  8. Set payment terms and print the calendar due date.
  9. Export to PDF so the client cannot alter it, and keep your editable working copy.
  10. Send to the accounts payable contact, not only the site contact, and log the date sent against the invoice number.

How Do Hourly and Fixed Price Invoices Differ?

Billing TypeWhat the Line Items ShowWatch Out For
HourlyDate, hours, rate, worker or tradeClients disputing hours without a daily log attached
Fixed priceContracted phase and lump sum amountExtras that were never converted to change orders
Progress drawScheduled value, percent complete, previously billedBilling ahead of completed work
Time and materialsHours plus material cost plus agreed markupMarkup percentage not being stated in the contract

Build It Once, Reuse It Every Time

Our Contractor Invoice Template is a spreadsheet with all eleven fields pre-built. Your business details, license number, tax rate, and payment terms are already filled in. Just enter the job, the lines, and the dates.

Get the Contractor Invoice Template

Frequently Asked Questions

What should be included on a contractor invoice?

The word Invoice, a unique invoice number, the issue date, your business name and contact details, your license number, the client's name and billing address, the job site address, itemized labor and materials, approved change orders, subtotal, tax and total due, and payment terms with a due date.

Does a contractor invoice need a license number?

Many states require the license number on contractor contracts and invoices, and it is standard practice in the trades regardless. Check your state licensing board.

What does a general contractor invoice look like?

Five blocks top to bottom: header, parties, job site and scope, an itemized line item table covering labor, materials, and change orders, and a footer with totals, payment terms, and payment instructions.

How do I invoice for change orders?

List each approved change order as its own line, referencing its change order number and approval date, separate from the base contract lines.

Should I send invoices as PDF?

Yes. PDF prevents accidental edits and displays the same on every device. Keep your editable copy for your own records.